KrampeHarex Lösungspfeil

TB-Anlage
ROBA

TB-Anlage ROBA Underwater foundation
Hamburg (Germany)

Building:
Concrete foundation
Building time:
Produced in July 2011
Concrete:
C 25/30
Fibre type:
DE 50/1,0 N
Fibre content:
40 kg / m3
Total volume:
48 m3
Building company:
Franki Pfahl
Effort class:
L1,2/0,9
Slump:
68 cm
Recipe:
320 Kg CEMIII-A/42,5, 80 Kg Flugasche, Sieblinie B/C 16, 1% v.Z.G. FM, 40 Kg DE 50/1,0 N
Specifics: The concrete foundation was installed three metres under water on auger piles, in the region of the Port of Hamburg. The concrete was placed by a diver. A combined reinforcement by SCE was calculated and C 25/30 with a performance category of L1,2/0,9 was required. The concrete was easily pourable.

TB-Anlage Roba, Hamburg (Deutschland)
TB-Anlage Roba, Hamburg (Deutschland)
TB-Anlage Roba, Hamburg (Deutschland)
TB-Anlage Roba, Hamburg (Deutschland)

Pferdekamp 6-8 | 59075 Hamm | Germany
T +49 (0) 23 81.977977 | F +49 (0) 23 81.977955 info@krampeharex.com Office hours
Mon-Thurs. 7:00 a.m. – 5:00 p.m.
Fri. 7:00 a.m. – 2:00 p.m. 
Shipping times
Mon-Fri 6:00 a.m. – 2:00 p.m.