KrampeHarex Lösungspfeil

Bridge Structure
S35

Bridge Structure S35
Bruck an der Mur (Austria)

Building:
Protective concrete
Building time:
June-July 2008
Concrete:
Transbeton ready-made concrete, Bruck/Mur, C 25/30/B3/GK 8/F 52
Fibre type:
DE 50/1.0 N
Fibre content:
20 kg/m3
Total volume:
1,000 m length, 12 m width, concrete thickness 8 cm
Gap partition:
6,00 m x 6,00 m
Specifics: Concrete work was carried out at temperatures over 30 degrees. Immediately following the application of the concrete, it was treated with at least 0.15/m2 evaporation protection. Concrete was applied using the wire mesh reinforcement method.

Brückentragwerk S35, Bruck an der Mur (Österreich)
Brückentragwerk S35, Bruck an der Mur (Österreich)
Brückentragwerk S35, Bruck an der Mur (Österreich)
Brückentragwerk S35, Bruck an der Mur (Österreich)
Brückentragwerk S35, Bruck an der Mur (Österreich)

Pferdekamp 6-8 | 59075 Hamm | Germany
T +49 (0) 23 81.977977 | F +49 (0) 23 81.977955 info@krampeharex.com Office hours
Mon-Thurs. 7:00 a.m. – 5:00 p.m.
Fri. 7:00 a.m. – 2:00 p.m. 
Shipping times
Mon-Fri 6:00 a.m. – 2:00 p.m.