KrampeHarex Lösungspfeil

Amazon
warehouse

Amazon warehouse
Rheinberg (Germany)

Bauteil:
Floor slab
Baubeginn / -zeit:
June – August 2011
Beton:
C 25/30
Fasertyp:
DE 50/1.0N
Gesamtvolumen:
22.000m³ steel fibre reinforced concrete
Bauunternehmen:
Bremer AG
Leistungsklasse:
1,2/0,9
Besonderheiten:

Approx. 80% of the floor slab was carried out with steel fibre reinforced concrete according to performance class.
The calculation was made by Schulz-Concrete-Engineering.
Here, a performance class of 1,2/0,9 was determined. Since the floor slab had to take a load-bearing function because of the high loads of the „Piektowers“, a concrete according to performance classes was stringently required.
In 2010 the concrete supplier has already successfully carried out performance class tests, so that the concrete could be delivered without any problems and further tests according to performance class.
The concrete sections were carried out without any joints.


Amazon Lager, Rheinberg (Deutschland)
Amazon Lager, Rheinberg (Deutschland)
Amazon Lager, Rheinberg (Deutschland)
Amazon Lager, Rheinberg (Deutschland)
Amazon Lager, Rheinberg (Deutschland)
Amazon Lager, Rheinberg (Deutschland)
Amazon Lager, Rheinberg (Deutschland)
Amazon Lager, Rheinberg (Deutschland)
Amazon Lager, Rheinberg (Deutschland)
Amazon Lager, Rheinberg (Deutschland)

Pferdekamp 6-8 | 59075 Hamm | Deutschland 
T +49 (0) 23 81.977977 | F +49 (0) 23 81.977955 info@krampeharex.com Bürozeiten
Mo.-Do. 7.00 – 17.00 Uhr | Fr. 7.00 – 14.00 Uhr
Versandzeiten
Mo.-Fr. 6.00 – 14.00 Uhr